| Tower 7 & 8 |
| Down Paymeht Plan (Rebate 9% on BSP) |
| On Application for Booking |
10 % |
| Within 45 Days from Allotment |
85 % + PLC + Lease Rent |
| At the Time of Notice for Possession |
5 % + IFMS |
| Construction Linked Payment Plan |
| On Application for Booking |
10 % |
| Within 45 Days from Allotment |
10 % |
| Within 90 Days from Allotment |
10 % |
| On Completion of Ground Floor Roof Plan |
10 % + 50 % Lease Rent |
| On Completion of 4th Floor Roof Slab |
7.5 % + 50 % Lease Rent |
| On Completion of 9th Floor Roof Slab |
10 % + 50 % PLC |
| On Completion of 18th Floor Roof Slab |
7.5 % |
| On Casting of Top Floor Roof Slab |
7.5 % |
| On Completion of Brick Work |
7.5 % |
| On Completion of Electric Conduiting & Wiring |
5 % |
| On Completion of Plumbing Work |
5 % |
| At the Time of Notice for Possession |
5 % + 100 % IFMS |
| Tower 9 |
| On Application for Booking |
10 % |
| Within 45 Days from Allotment |
10 % |
| Within 90 Days from Allotment |
10 % |
| Within Completion of Ground Floor Roof Slab |
10 % + 50 % Lease Rent |
| On Completion of 5th Floor Roof Slab |
7.5 % + 50 % Lease Rent |
| On Completion of 10th Floor Roof Slab |
7.5 % + 50 % PLC |
| On Completion of 15th Floor Roof Slab |
7.5 % + 50 % PLC |
| On Completion of 20th Floor Roof Slab |
7.5 % |
| On Casting of Top Floor Roof Slab |
7.5 % |
| On Completion of Brick Work |
7.5 % |
| On Completion of Electric Conduiting & Wiring |
5 % |
| On Completion of Plumbing Work |
5 % |
| At the Time of Notice for Possession |
5 % + 100 % IFMS |